PROBLEMS
13.132 Draw the PERT network associated with the following activities.
Immediate Predecessor
A –
B A
C A
D B
E B
F C
G D
H E, F
ANSWER:
13.133 Given:
Activity Optimistic Most Likely Pessimistic
A 3 4 5
B 6 7 14
C 2 3 10
D 0.5 1 1.5
E 6 9 12
F 4 5 12
G 1 3 11
Determine:
(a) the critical path
(b) the probability that the project will be completed in 22 weeks
ANSWER:
13.134 The following represent activities in a major construction project. Draw the network to represent this situation.
Activity Immediate Predecessor
A –
B –
C A
D B
E B
F C, D
G E
H F, G
13.135 A small software development project has five major activities. The times are estimated and provided in the table below. Find the expected time for completing this project.
Activity Immediate
Predecessor a m b
A 2 5 8
B 3 6 9
C A 4 7 10
D B 2 5 14
E C 3 3 3
(a) What is the expected completion time for this project?
(b) What variance would be used in finding probabilities of finishing by a certain time?
13.136 A project has an expected completion time of 40 weeks and a standard deviation of 5 weeks. It is assumed that the project completion time is normally distributed.
(a) What is the probability of finishing the project in 50 weeks or less?
(b) What is the probability of finishing the project in 38 weeks or less?
(c) The due date for the project is set so that there is a 90 percent chance that the project will be finished by this date. What is the due date?
13.137 Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below.
Activity Normal Time Crash Time Normal Cost Crash Cost Immediate
Predecessor
A 4 3 2000 2600 –
B 2 1 2200 2800 –
C 3 3 500 500 –
D 8 4 2300 2600 A
E 6 3 900 1200 B
F 3 2 3000 4200 C
G 4 2 1400 2000 D,E
(a) What is the project completion date?
(b) What is the total cost required for completing this project on normal time?
(c) If you wish to reduce the time required to complete this project by one week, which activity should be crashed, and how much will this increase the total cost?
13.138 Draw the PERT network associated with the following activities.
Immediate Predecessor
A –
B A
C A
D B
E B
F C, E
G A, D
H F
I F
J G, H, I
13.139 Given:
Activity Optimistic Most Likely Pessimistic
A 3 4 5
B 6 7 14
C 2 3 10
D 6 9 12
E 4 5 12
F 1 3 11
G 1 2 9
H 2 5 8
I 1 4 7
Determine:
(a) the critical path
(b) the probability that the project will be completed in 22 weeks
13.140 The following table represents activities in a major construction project. Draw the network to represent this situation.
Activity Immediate Predecessor
A –
B –
C B
D B
E A, C
F D
G E, F
H B
I G, H
13.141 A small software development project has four major activities. The times are estimated and provided in the table below. Find the expected time for completing this project.
Activity Immediate
Predecessor a m b
A 2 5 8
B 3 6 9
C A 4 7 10
D B 2 5 14
E D 3 3 3
F C 6 8 10
G E, F 1 1 1
H C 6 10 14
I G, H 3 4 5
(a) What is the expected completion time for this project?
(b) What variance would be used in finding probabilities of finishing by a certain time?
13.142 A project has an expected completion time of 50 weeks and a standard deviation of 7 weeks. It is assumed that the project completion time is normally distributed.
(a) What is the probability of finishing the project in 50 weeks or less?
(b) What is the probability of finishing the project in 55 weeks or more?
(c) What is the probability of finishing the project in 44 weeks or less?
(d) The due date for the project is set so that there is a 90 percent chance that the project will be finished by this date. What is the due date?
13.143 Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below.
Activity Normal Time Crash Time Normal Cost Crash Cost Immediate
Predecessor
A 4 3 2,000 2,600 –
B 5 3 2,200 2,800 –
C 3 3 500 500 –
D 8 4 2,400 2,600 A
E 6 3 900 1,200 B
F 3 2 3,000 4,200 C
G 4 2 1,700 2,000 D,E
(a) If you wish to reduce the time required to complete this project by two weeks, which activity(ies) should be crashed, and how much will this increase the total cost?
(b) What would be the added cost if you wanted to complete the project in the minimum time possible?
SHORT ANSWER/ESSAY
13.144 PERT is the acronym for
13.145 CPM is the acronym for
13.146 In a PERT analysis, how is the optimistic time defined?
13.147 In a PERT analysis, how is the most likely time defined?
13.148 In PERT analysis, how is the pessimistic activity time defined?
13.149 In PERT/CPM, what is meant by the critical path?